Sunday 24 November 2019

Job 652 was recently completed. The following data have been recorded on its job cost sheet:

Job 652 was recently completed. The following data have been recorded on its job cost sheet:




Direct materials $ 61,900
Direct labor-hours
1,229 DLHs
Direct labor wage rate $ 12 per DLH
Number of units completed
4,100 units

The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $36 per direct labor-hour.
Required:
Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2 decimal places.)


Unit product cost ?   

Contact Us For Tutoring:

Name

Email *

Message *