During 2016, YellowCard constructed a small manufacturing
facility specifically to manufacture one particular accessory.
YellowCard paid the construction contractor $5,269,000 cash (which
was the total contract price) and placed the facility into service
on January 1, 2017. Because of technological change, YellowCard
anticipates that the manufacturing facility will be useful for no
more than 10 years. The local government where the facility is
located required that, at the end of the 10-year period, YellowCard
remediate the facility so that it can be used as a community
center. YellowCard estimates the cost of remediation to be
$424,800.